Express and implied terms in construction contracts
The rights and obligations of parties to a contract are defined by its terms. Express terms are those that have been explicitly agreed by both parties and can be oral or in writing.
However, the express terms do not necessarily constitute all the relevant terms of the agreement. In certain circumstances the courts are prepared to imply terms into a contract provided such terms are necessary to give business efficacy to the agreement.
The leading case on implied terms is The Moorcock case (1889). In that case Bowen LJ stated:
"Now, an implied warranty, or, as it is called, a covenant in law, as distinguished from an express contract or express warranty, really is in all cases founded upon the presumed intention of the parties, and upon reason. The implication which the law draws from what must obviously have been the intention of the parties, the law draws with the object of giving efficacy to the transaction and preventing such a failure of consideration as cannot have been within the contemplation of either side; and I believe if one were to take all the cases, and there are many, of implied warranties or covenants in law, it will be found that in all of them the law is raising an implication from the presumed intention of the parties with the object of giving the transaction such efficacy as both parties must have intended that at all events it should have".
Terms may be implied as a matter of law. That is to say they are implied as a matter of policy and are of general application to all contracts. Further terms may be implied as a matter of fact. That is to say as a matter of construction of the presumed intention of the parties to a particular contract. The case of Foley v Classique Coaches Limited (1953) is an illustration of a term being implied as a matter of fact.
Whilst a term will not be implied unless in the particular circumstances of each case it is reasonable to imply such a term, this does not mean that a term will be implied merely because it is reasonable. For example, Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board (1973) where the court refused to imply a term to render a harsh contract more reasonable.
Further, a term will not be implied if it is inconsistent with the express terms of the contract. In Martin Grant & Co Ltd v Sir Lindsay Parkinson & Co Ltd, the Court of Appeal refused to imply a term in a building subcontract:
‘that (a) the [main contractors] would make sufficient work available to the [sub-contractors] to enable them to maintain reasonable progress and to execute their work in an efficient and economic manner; and (b) the main contractors should not hinder or prevent [the sub-contractors] in the execution of the sub-contract works' where the express conditions of the sub-contract provided for a 'beck and call' obligation on the sub-contractor; that is to say the sub-contractor was obliged to carry out his works '... at such time or times and in such manner as the [main contractor] shall direct or require'.
[edit] Related articles on Designing Buildings Wiki
- Agency.
- Clause.
- Collateral warranty.
- Construction contract.
- Contract v tort.
- Defective Premises Act.
- Design liability.
- Defective Premises - Liability and Measure of Damages.
- Fitness for purpose.
- Modifying clauses in standard forms of contract.
- Reasonable skill and care.
- Recitals.
- Zennstrom & Anor v Fagot & Ors.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.